Complete Process

Your Journey to Solar Energy

From your first quote to enjoying years of clean energy savings - here's everything you need to know about going solar in Cyprus

Form to Offers
Instant
📋
EAC Approval
1-2 weeks
🔧
Installation
1-2 days
📅
Total Process
4-8 weeks
Step by Step

Complete Installation Process

Everything you need to know from start to finish

Step 1

Get Personalized Offers

Fill up the form to receive personalized offers from various solar providers in Cyprus. Compare prices, equipment, and warranties all in one place.

Step 2

Analyze & Compare

Review and compare the offers side by side. Look at system specifications, pricing, warranties, and provider reputation to make an informed decision.

Step 3

Choose Your Package

Pick the right offer that fits your budget and needs. Our support team is happy to help you pick the right package in case of uncertainty.

Step 4

Apply for Solar Grant

Download the desired offer and submit it for the Solar Grant in Cyprus. The government offers generous subsidies up to €1,500 for regular applicants.

Step 5

Payment & Grant Decision

Wait for the grant approval, or you can make the first payment for the desired offer to continue with the installation process while waiting.

Step 6

Document Submission

After the payment, you will receive an email from the installation company to upload all the required documents for submitting your application to EAC.

Step 7

Site Survey

The installation company's structural and electrical engineers will organize a site survey to assess your property and finalize the installation plan.

Step 8

EAC Application

The installation company will submit your complete application with the engineering and electrical plans and all auditing documents to EAC for their approval. This usually takes 1-2 weeks.

This step is skipped for off-grid systems
Step 9

Installation

After EAC approval, the installation company will organize an installation date. The installation typically takes 1-2 days to complete.

Step 10

Inspection Request

The installation company electrician will submit the inspection request to EAC for the final inspection and installation validation.

Step 11

EAC Inspection & Meter Installation

EAC will inspect the site and the whole installation. If everything is fine, the net-metering/net-billing meter will be installed and the contract will be signed.

Step 12

Handover & Go Live

The installation company will hand over the complete system to you. You will start enjoying the benefits of your solar investment immediately!

After Installation

What Happens Next?

Your ongoing solar experience and support

Client Portal & Live Monitoring

You will have access to a client portal where you can monitor your order status and watch your system's production in real-time.

AI-Powered System Monitoring

Luxa Energy offers an AI monitoring scheme that monitors your system throughout the year and alerts the installation company as soon as something is off.

Regular Maintenance

We recommend washing your solar panels every 2-3 months for maximum solar harvest. You can order a recurring service from one of our partners to take care of this for you.

Long-Term Support

In about 10 years, the installation company will contact you again for replacing the inverter and/or batteries if you have installed any.

Common Questions

Frequently Asked Questions

Everything you need to know about solar installation in Cyprus